La nuova sede del Caltrans - Dipartimento dei trasporti della California

Design and construction of the new California Department of Transportation (Caltrans) District 7 Headquarters building, to serve 1,850 Caltrans employees and 500 employees of the Los Angeles Department of Transportation. The building, which also features public amenities and a significant street presence, is the first to be commissioned under the State of California’s Design Excellence Program.

 

Location: 100 South Main Street, Los Angeles, CA

owner: State of California, Department of General Services

design/build team.
Main & First Design/Build Associates, Inc.
executive architect: mOrphosis; general contractor: The Clark Construction Group, Inc.
developer: Urban Partners

key dates:
design commission awarded through competition: November 2001
design/build commence: February 2002; construction start: May 2002
tenant occupancy begins: September 2004; opening: September 27, 2004Location:
100 South Main Street, Los Angeles, CA

owner:
State of California, Department of General Services

design/build team.
Main & First Design/Build Associates, Inc.
executive architect: mOrphosis
general contractor: The Clark Construction Group, Inc.
developer: Urban Partners

key dates:
design commission awarded through competition: November 2001
design/build commence: February 2002 ; construction start: May 2002
tenant occupancy begins: September 2004 ; opening: September 27, 2004

 
building cost: $165 million
total project cost: $190 million

size:
1.05 million gross square feet:
750,000 gsf office building, 300,000 gsf underground parking garage

principal exterior: Steel structure; Cynar-coated perforated aluminum panels; Eternit
materials: Cement panels; Sarnafil membrane; glass

principal interior: Painted drywall; exposed polished concrete in lobby; carpet; wire mesh
materials: Ceiling panels; linear perforated ceiling panels

mOrphosis team:
Thom Mayne, Principal; Silvia Kuhle, Project Manager; Pavel Getov, Project Architect
Anthony Mrkic, Job Captain, Chandler Ahrens, Irena Bedenikovic, Tim Christ, Mario Cipresso, Ben Damron, Marty Doscher, Paul Gonzales, Salvador Hidalgo Olivia Jukic, Ted Kane, Dwoyne Keith, Kristina Loock, Jean Oei, Axel Schmitzberger, Martin Summers, Daynard Tullis

clark construction: Richard Heim, President
team: John Williams, Senior Vice President; Marc Kersey, Project Executive
urban partners: Dan Rosenfeld, Partner; team: Laura Benson, Project Manager
Photos by Roland Halbe.
Pianta e sezione dwg di un sistema di schermatura con passerella di manutenzione
Indice dwg
L o s  A n g e l e s  2 0 0 4   -   C a l t r a n s   D i s t r i c t  7
Arredi dwg

DVD banca dati archweb dwg
 
Sono presenti nella nostra banca dati  file dwg di qualsiasi genere, dalla tipologia edilizia, al dettaglio architettonico.  Informazioni per avere l'intera banca dati dwg 2D/3D  >>
architetture I archivi I blog architettura I tecnologie I eventi I  textures
tesi di laurea I utilità disegno I geometrie I dwg
Copyright © Archweb.it  Tutti i diritti riservati - Contatti - disclaimer  - Facebook - Pubblicità
H O M E